SiteScout

Planning intelligence for people who build.

← Back to the lead desk
Fingal Weekly Planning02 Jul 2026

F26A/0577

Tesco Distrabution Centre, Lanistown, Donabate, Co.Dublin

Lead potentialHigh

Substantial sewer infrastructure project with pumping station, 1.5km rising main, and 581m gravity sewer along public roads.

Planning stageNew Application
Project typeSite Infrastructure
Development sectorInfrastructure Utilities
Matched trades4

Source description

What is being proposed

The Development will consist of the inclusion of a new foul sewer pumping station and 24-hour holding tank. new pumped foul sewer rising main and portion of gravity foul sewer plus associated decommissioning and removal of an existing on-site wastewater treatment plant. The works will include: (i) The redirection of the wastewater flow from the existing wastewater treatment plant to the proposed new foul sewer pump station (33m length of 225mm gravity foul sewer); (ii)1,524m of 100mm rising main from the new pump station routed along Cobbe's Lane public road to Turvey Avenue public road; and (iii) 581 m of 225mm gravity sewer from the aforementioned rising main to connect to the existing Uisce Eireann foul sewer on Turvey Avenue adjacent to Turvey Woods Residential Development.

Opportunity fit

Why these trades match

4 evidence-led matches
01

Civil Utilities

High

New foul sewer pumping station, holding tank, rising main, and gravity foul sewer with decommissioning of existing wastewater treatment plant.

02

Groundworks Drainage

High

Extensive sewer installation including 1,524m rising main and 581m gravity sewer along public roads.

03

Main Contracting

Medium

Substantial multi-component sewer infrastructure project suited to a main contractor.

04

Plant Hire

Medium

Long-distance sewer installation along public roads implies significant excavation and plant use.