Fingal Weekly Planning22 Jun 2026

F26A/0541E

Dun Aoibhinn, New Road, Ballymastone, Donabate, Co. Dublin, K36 A593

Lead potentialHigh

Four new dwelling houses with roads, drainage, SUDS, landscaping and site development works represent a substantial residential construction package.

Planning stageNew Application
Project typeNew Build
Development sectorResidential
Matched trades6

Source description

What is being proposed

Planning Permission is sought for a residential development consisting of (i) Four x four bedrooms detached dormer bungalows; (ii) New revised vehicular access off New Road, Donabate; (iii) Internal road access, boundary fencing, SUDS, drainage, public open space, landscaping and all ancillary site development works; (iv) Decommissioning of existing Biocycle treatment plant and connection of foul sewer from existing house to foul drainage system.

Opportunity fit

Why these trades match

6 evidence-led matches
01

Groundworks Drainage

High

Internal road access, SUDS, drainage, foul sewer connection and site development works are explicitly specified.

02

Main Contracting

High

Four new dormer bungalows with roads, drainage, SUDS, landscaping and site works represent substantial multi-package construction.

03

Civil Utilities

Medium

Decommissioning of Biocycle plant and foul sewer connection involve utility works.

04

Concrete Masonry

Medium

Four new dwelling houses imply substantial blockwork, brickwork and foundations.

05

Landscaping Siteworks

Medium

Public open space, landscaping and boundary fencing are explicitly stated.

06

Roofing

Medium

Dormer bungalows require new roof construction and dormer works.