Civil Utilities
HighConnection to underground foul and storm water drainage network and installation of utility ducts and cables are explicitly stated.
Planning intelligence for people who build.
Within the townland of Milltown, located to the north of Peamount Road (R120), Newcastle, Co. Dublin
Two major ICT facilities totalling 30,518 sq.m on an 8.2 hectare site with generators, substations, drainage, roads and landscaping represent a clearly specified, substantial construction programme.
Source description
Demolition of existing two storey dwelling of 'Bulmer' and associated outbuildings and demolition of the existing single storey house of 'Little Acre' and its associated garage and other buildings; demolition of single storey stable building on the overall site; construction of 2 two storey Information Communication Technology (ICT) facilities each with three storey plant levels and associated ancillary development which will have a gross floor area of 30,518sq.m on an overall site of 8.2 hectares;…
Demolition of existing two storey dwelling of 'Bulmer' and associated outbuildings and demolition of the existing single storey house of 'Little Acre' and its associated garage and other buildings; demolition of single storey stable building on the overall site; construction of 2 two storey Information Communication Technology (ICT) facilities each with three storey plant levels and associated ancillary development which will have a gross floor area of 30,518sq.m on an overall site of 8.2 hectares; 1 two storey ICT facility (building A) will be located to the south-east of the site and will have a gross floor area of 15,196sq.m including 18 emergency generators located at ground and first floor level within a compound to the north-eastern side of the ICT facility with associated flues that will be 25m in height and will be grouped in four groups of four and 1 group of two flues (18 flues overall); 1 two storey ICT facility (building B) will be located to the north-west of Building A and centrally within the overall site and will have a gross floor area of 15,196sq.m including 18 emergency generators located at ground and first floor level within a compound to the north-eastern side of the ICT facility with associated flues that will be 25m in height and will be grouped in four groups of four and 1 group of two flues (18 flues overall); each of the two ICT facilities will include data storage rooms, associated electrical and mechanical plant rooms, loading bays, maintenance and storage spaces, office administration areas; 2 pump rooms of 25sq.m each (4 overall - 100sq.m) plus water storage tanks and plant as well as a separate house generator that will provide emergency power to the admin and ancillary spaces; each generator will also include a diesel belly tank with a single refuelling area to serve the proposed emergency generators; 1 temporary and single storey substation (26sq.m); ancillary site development works including attenuation ponds and the installation and connection to the underground foul and storm water drainage network and installation of utility ducts and cables; other ancillary site development works will include hard and soft landscaping throughout the site, lighting, fencing, signage, central services road, security gate, sprinkler tank house and 80 car parking spaces and 17 sheltered bicycle parking spaces; the development will be enclosed with landscaping to all frontages including a wetland to the south-east and will be accessed from the Peamount Road (R120) located within the townland of Milltown on lands that contain the 2 residential properties of 'Little Acre' and 'Bulmer' as well as agricultural lands and buildings which are located to the north of the Peamount Road and the lands to the north and within the overall site are subject to a concurrent application for a Power Generation Facility under Reg. SD20A/0058; An Environmental Impact Assessment Report (EIAR) is included with the application.
Opportunity fit
Connection to underground foul and storm water drainage network and installation of utility ducts and cables are explicitly stated.
Demolition of two dwellings, outbuildings, garage and stable building is explicitly stated.
ICT facilities with electrical plant rooms, 18 emergency generators per building, substation and utility cables are explicitly described.
Explicit attenuation ponds, underground foul and storm water drainage network, utility ducts, central services road and 80 car parking spaces are stated.
ICT data storage rooms with mechanical plant rooms and generator flues explicitly require substantial mechanical ventilation systems.
Two large ICT facilities totalling 30,518 sq.m with plant levels, generators, substations and extensive site works represent a substantial multi-package construction programme.
Hard and soft landscaping, wetland to south-east, fencing and security gate are explicitly described.
Coordinated mechanical, electrical and public-health design for ICT facilities with generators and plant is strongly implied.
Large-scale site on 8.2 hectares with demolition, drainage and construction implies material plant-intensive operations.
A 30,518 sq.m development with EIAR is a substantial project clearly requiring cost planning and procurement.
Two-storey ICT facilities with three-storey plant levels and 25m generator flues strongly imply substantial structural steel framing.