Demolition
HighDemolition of existing warehouse/offices (954 sqm gross) is explicitly stated.
Planning intelligence for people who build.
A o.579 h. Site at Partlickstown, Navan Road,, Mulhuddart, Dublin 15., D15K30K
Substantial project combining demolition of 954 sqm warehouse and construction of a new three-storey 1,752 sqm warehouse with offices, yard and infrastructure.
Source description
The development will consist of : (i) Demolition of existing warehouse/offices (954 sqm gross); (ii) Construction of new three storey in height warehouse including ancillary offices and welfare facilities over three floors (1,752sqm gross); (iii) the provision of an associated service yard including wash down area, a new internal access road, pedestrian pathways, car parking, cycle parking; (iv) the provision of a sub-station, boundary changes including the relocation of the existing gate and the provision of a new pedestrian gate, planting, and; (v) SuDS and utility infrastructure as well as all other associated site services and site development works. Additional Information Received 21/07/2026
Opportunity fit
Demolition of existing warehouse/offices (954 sqm gross) is explicitly stated.
Demolition plus new three-storey warehouse with offices, service yard, substation and infrastructure is a substantial multi-package project.
New three-storey warehouse of 1,752 sqm gross clearly centres on structural steel framing.
SuDS and utility infrastructure are explicitly described.
Provision of a sub-station is explicitly listed.
Service yard, internal access road, car parking and SuDS infrastructure are explicitly described.
Planting and boundary changes are explicitly listed.